|
|
|
Italian Cooperation in
Egypt |
|
Development Cooperation Projects |
|
Esna
dam construction |
 |
Project financed through:
SOFT LOAN :
110 M$
GRANT
: 20 M$
OTHER FINANCING :
GOE
(GOVERNMENT OF EGYPT) : 188 M$ EQUIVALENT
MAIN CONTRACTOR :
CONSORZIO EUROCEB – ITALY
EUROPEAN CONSORTIUM FOR ESNA BARRAGE FORMED BY:
IMPREGILO
S.P.A - COGEFAR S.P.A - ANSALDO S.P.A
CONTRACT SIGNATURE :
MARCH 1989
CONSTRUCTION PERIOD:
1989 - 1994 |
|
|
Introduction
Agriculture is
one of the most important sectors of the Egyptian economy and
occupies a large part of the country's workforce. Its output is
limited by the lack of cultivable land and water resources.
The old
Esna dam was the principal source of irrigation supply for
the Governorate of Qena, supplying water to 125,000
hectares of agricultural land. Built in 1908 with the
piers made of sandstone rubble masonry around a centre of
hydraulic mortar and then repaired and reinforced in 1947, if
has become obsolete and no longer has the necessary impounding
capacity required for agricultural needs, nor is it able to
efficiently manage the river traffic any longer. In addition, if
did not exploit; the available head for electric generation. |
|
History of the project
Starting
in 1978, various international organizations and major
consulting companies performed studies on the existing dam and
on the best solutions to be adopted, coming to the conclusion
that it was no longer advantageous to repair the old dam and
that a new one downstream the present one should be constructed
.
Based upon a
design executed by the French company Sogreah, in 1986 the
Egyptian Ministry of Public Works and Water Resources, in
agreement with the Ministry of Energy, announced an
international tender for the construction of the new dam,
which also included a hydroelectric plant capable of
exploiting the available head producing over 600 GWh of
electrical energy a year.
The fundamental objectives of the project may be summarized as
follows:
1)
Ensuring better regulation and use of irrigation water,
permitting irrigated areas to be maintained and expanded in
future years;
2)
Handling the expected future erosions of the river bed;
3)
Producing electrical energy by using the available head;
4)
Permitting better navigation conditions by constructing a lock
with a boat passage capacity greater than that of the old one
and sufficient to meet the expected needs of the river traffic;
5)
Constructing an alternative road on top of the dam to connect
the two banks.
The call for tenders for this project, which was of extremely
high priority for the country, aroused the interest of various
nations, including Italy, who expressed their willingness to
contribute to the financing of the Project.
14 bids were submitted and publicly opened in December 1986 by
groups leadered by companies from 10 different countries.
The offer of
the Italian group, which consists of the Italian companies
Impregilo, the group leader, and Cogefar (now merged
in a single company known as Impregilo S.p.A.) for the civil
works and GIE (now Ansaldo Energia) with the
participation of the Rumanian Romenergo for the hydro-mechanical
portion, was the best one.
The contract
was signed in March 1989 and the construction began
immediately. |
|
The works
The
works started on April 1, 1989,
when the order to proceed was given. The residential camps for
Employer's and Engineer's personnel, and the one for the foreign
staff were built, as well as the workshops, warehouses, offices
and plants necessary for the construction.
At the same
time, a cofferdam was realized to separate the left zone of the
Nile in which the concrete works were located: navigation lock,
powerhouse, spillway.
A geologic
campaign was performed in order to control and define
certain basic data found in the tender documents, and the final
design was developed, the civil engineering portion of which was
assigned to the Italian company ELC - Electroconsult of Milan.
The embankment was waterproofed by means of a diaphragm wall 40
meters deep, and the entire area it enclosed was dewatered and
kept dry by a special pump network, while the excavations and
concrete works were performed. |
|
As
the entire foundation of the works is on sand, diaphragm walls
up to 40 meters deep were constructed to prevent the passage of
water. Both the diaphragm wall under the dam and that one in the
temporary cofferdam were constructed by a group of specialized
subcontractors, leadered by RODIO of Casalmaiocco
(Milan).
All the concrete works, about 300,000 cu m, were constructed
within 20 months, with production peaks of 25,000 cu m a
month.
For concrete pouring, moving the forms and reinforcement steel
placing, seven enormous tower cranes, sliding on rails were used
so that they were able to serve the entire area involved in the
works.
When the temporary cofferdam was removed, the navigation along
the Nile was diverted from the right side of the river to the
left, through the navigation lock; the right side was closed by
a rock barrier which forced the entire flow of water to pass
through the spillway, and then the closure dam was constructed
in granular materials with protections in rockfill and a
waterproofing diaphragm wall.
At the same time as the civil
works, the electromechanical group supplied and erected the
hydromechanical parts, the turbines, the auxiliary equipment and
plants and the electrical parts.
|
|
General
description of the project
The
contract includes the construction design of the Project, the
construction, training of personnel and maintenance of the plant
for two years and includes the following works and machinery:
Civil Works
-
A
concrete powerhouse for No. 6-15MW bulb turbines.
-
A
concrete spillway with 11 openings, suitable for 12 m radial
gates with the possibility of closure by means of stoplogs and
the maximum discharge capacity of 7,000 m3/sec.
-
A
concrete navigation lock 160 m long, 17 m wide and of minimum
3 meters draught.
-
A closure
dam in loose materials.
-
Canals,
buildings, roads and additional works. .
-
Employer's and Engineer's camp. .
-
Waterproofing operations (permanent Diaphragm Wall more than 1
kilometer long and about 40 meters deep).
-
Temporary works for river diversion; cofferdam to include the
area with the concrete works; temporary diaphragm wall about 2
kilometers long and 40 meters deep; dewatering.
-
Works
and infrastructures for the construction:
plants,
quarries, camps and services for foreign and local personnel.
|
|
The main quantities of works are:
|
Earth excavations
Dredging
Quarry excavations
Embankments and rock protections
Plastic and bentonite diaphragm walls
Concrete
Concrete forms
Reinforcing steel |
2,100,000 cu m
2,980,000 cu m
2,000,000 cu m
910,000 cu m
101,000 sq m
290,000 cu m
198,000 sq m
23,500 tons |
|
|
Electromechanical Works:
90 MW
electric plant including:
-
n.6
Kaplan type horizontal turbines 15 MW each, with 3 blades,
rotor diameter 6.25 m, nominal head 5.7 m.
-
n.6-15
MW generators, voltage 11 KV, power factor 0.85, brush less
excitation.
-
Control
systems, medium and low voltage equipment, 60/30/30 MVA
transformers, aerial lines.
-
132 KV
elevating switchyard with aerial transmission lines.
-
Auxiliary systems such as air compression, water treatment,
drainage, fire prevention, air conditioning and ventilation,
etc.
-
n. 2
90 ton gantry cranes
-
n. 2
15 ton cranes
-
n.11
radial gates for spillway (12x12.9 ml
-
n. 6
sets of stoplogs for maintenance
-
n. 2
gates for the navigation lock
-
n. 1
Bascule bridge, 17 m long and 12 m wide.
|
|
Value of contract and financing
The initial
value of the contract for the civil works is 67 million Egyptian
pound and a foreign currency component equivalent to 48 million
dollars; that one for the electromechanical supply and erection
is 18 million Egyptian pound and a foreign currency component
equivalent to 77 million dollars.
The total amounts to
160 million dollars at 1989 exchange rates.
The foreign currency portions were
mainly financed by the Italian Government through the Italian
Agency for International Cooperation, with minor portions by
Austrian and Rumanian loans. |
|
|
|